Progress at the Agnews Site

October 2019

More "firsts" at Agnews as the first structural steel installation takes place on the elementary school site. The cranes were delivered on October 4, steel was delivered early morning on October 7, and by the end of the day, the frame of Building D was up — impressive work team!

The middle school construction team has been busy working on the future two-story building — building G. Steel installation for building G, which will contain administration on the first floor and classrooms on the second, occurred on the week of October 14. 

As of the first week of November, we have steel erected in four of the nine buildings at the elementary and middle school sites. Concrete curbs and gutter placement at the elementary school site has also started.

Visit the Agnews webpages for regular updates.