Parking Lot Reconfiguration at Scott Lane Elementary School

We are excited to announce that the parking lot work at Scott Lane Elementary is complete.

Project Updates:

October 4, 2024: The EV chargers are now activated and ready for use. 

October 4, 2024: The EV chargers are now activated and ready for use. 

August 21, 2024: Outdoor learning spaces are complete with picnic tables and planters, ready for students to start planting.

August 21, 2024: Outdoor learning spaces are complete with picnic tables and planters, ready for students to start planting.

August 9, 2024: The striping of the lower and upper grade hardcourts is complete.

August 9, 2024: The striping of the lower and upper grade hardcourts is complete.

August 5, 2024: The parking lot officially opened today for staff's return. EV chargers will be installed this week.

August 5, 2024: The parking lot officially opened today for staff's return. EV chargers will be installed this week.

August 2, 2024: Concrete benches in the new entry plaza were placed by crane this morning.

August 2, 2024: Concrete benches in the new entry plaza were placed by crane this morning.

August 1, 2024: Paving of the parking lot is complete, and the striping has been laid out, ready for painting tomorrow.

August 1, 2024: Paving of the parking lot is complete, and the striping has been laid out, ready for painting tomorrow.

July 31, 2024: The crew is halfway through the parking lot by late morning, with asphalt paving underway.

July 31, 2024: The crew is halfway through with asphalt paving the parking lot by late morning, 

July 31, 2024: Asphalt paving of the parking lot began this morning.

July 31, 2024: Asphalt paving of the parking lot began this morning.

PLazza

July 30, 2024: Trees are being planted at the new entry plaza, and the asphalt work for the parking lot is set to begin tomorrow.

July 30, 2024: New landscaping is being installed in front of the kindergarten yard.

July 30, 2024: New landscaping is being installed in front of the kindergarten yard.

July 26, 2024: The raised crosswalks and walkways are complete, and parking lot paving starts next week.

July 26, 2024: The raised crosswalks and walkways are complete, and parking lot paving starts next week.

July 23, 2024: The raised crosswalks are being installed, and new light poles are up in the parking lot.

July 23, 2024: The raised crosswalks are being installed, and new light poles are up in the parking lot.

July 23, 2024: The concrete is curing, and the new entry plaza is ready for landscaping, trees, and benches.

July 23, 2024: The concrete is curing, and the new entry plaza is ready for landscaping, trees, and benches.

July 23, 2024: Driveway and sidewalk replacement along Scott Boulevard.

July 23, 2024: Driveway and sidewalk replacement along Scott Boulevard.

July 17, 2024:

  • Traffic lane re-striping on Scott Blvd. between Royal Ave. and Cabrillo Ave. is scheduled to begin the week of July 22nd and will span a duration of 3 to 4 days. During this period, temporary lane closures and traffic diversions will be in place. 
  • For more information click on: 7/17 Notification to Neighbors
July 17, 2024: Asphalt work has begun at the lower grade playground.

July 17, 2024: Asphalt work has begun at the lower grade playground.

July 17, 2024: Concrete pouring has started at the new entry plaza.

July 17, 2024: Concrete pouring has started at the new entry plaza.

July 16, 2024: The contractor is setting up forms in preparation for pouring concrete at the new entry plaza.

July 16, 2024: The contractor is setting up forms in preparation for pouring concrete at the new entry plaza.

July 16, 2024: New trees have been delivered to the site and will be planted soon.

July 16, 2024: New trees have been delivered to the site and will be planted soon.

July 9, 2024: The form and concrete pours for all curbs in the parking lot are nearly complete.

July 9, 2024: The form and concrete pours for all curbs in the parking lot are nearly complete.

July 9, 2024: Grading work is in progress

July 9, 2024: Grading work is in progress.

July 1, 2024: The concrete curb along the new pick-up/drop-off lane in the parking lot was poured today.

July 1, 2024: The concrete curb along the new pick-up/drop-off lane in the parking lot was poured today.

June 28, 2024: The forms for the new pick-up/drop-off curb in the parking lot are ready for the concrete pour scheduled for next week.

June 28, 2024: The forms for the new pick-up/drop-off curb in the parking lot are ready for the concrete pour scheduled for next week.

June 13, 2024: Significant progress has been made since the last day of school.  Portables 21 and 22 have been successfully relocated, the parking lot has been completely demolished, and the demolition of the hardcourts has begun.

June 13, 2024: Significant progress has been made since the last day of school.  Portables 21 and 22 have been successfully relocated, the parking lot has been completely demolished, and the demolition of the hardcourts has begun.

May 29, 2024

  • The parking lot entry and exit will remain open on May 31st until 6:00pm.
  • The parking lot and school site will be closed for construction beginning June 1st.
  • For more information click on: 5/29 Notification to School

May 16, 2024:

  • There will be a pedestrian path detour next to the front driveway vehicle entrance starting May 17th so that the contractor can begin work on a new waterline for the fire hydrants.
  • Grading for new portable foundations and work on the new driveway on Cabrillo Ave. will begin the week of May 20th.
  • For more information click on: 5/16 Notification to School

May 10, 2024:

  • New driveway work on Cabrillo Ave. to begin May 20th.
  • Removal of perimeter fencing to begin June 3rd.
  • Installation of perimeter fencing to begin June 20th.
  • Re-striping of traffic lanes on Scott Blvd. to begin July 22nd.
  • For more information click on: 5/10 Notification to Neighbors

May 8, 2024:

  • The date for work to begin on the new driveway on Cabrillo Ave. has moved to May 20th.
  • Beginning June 1st, the school site will be closed for construction.
  • For more information click on: 5/8 Notification to School

April 12, 2024:

  • In order to complete the parking lot and areas directly influencing students prior to the start of school in August 2024, the contractor will start preparing the site during the spring break, April 15th to April 18th.
  • For more information click on: 4/12 Notification to Neighbors

March 29, 2024:

  • The award of contract to SC Builders was approved at the March 28th Board Meeting. 

March 27, 2024:

Questions

If you have questions or would like to be added to the listserv for this project, please email us at ScottLaneConstruction@scusd.net.