Skip To Main Content

Parking Lot Reconfiguration at Scott Lane Elementary School

We are excited to announce that the work on this summer's parking lot and site improvement project is well underway.  As part of our commitment to enhancing our school facilities, we are thrilled to share some important updates regarding the project timeline and next steps. 

Updates

Scott Lane

July 23, 2024: The raised crosswalks are being installed, and new light poles are up in the parking lot.

Scott Lane New Entry Plaza

July 23, 2024: The concrete is curing, and the new entry plaza is ready for landscaping, trees, and benches.

Driveway and sidewalk replacement along Scott Boulevard.

July 23, 2024: Driveway and sidewalk replacement along Scott Boulevard.

July 17, 2024:

  • Traffic lane re-striping on Scott Blvd. between Royal Ave. and Cabrillo Ave. is scheduled to begin the week of July 22nd and will span a duration of 3 to 4 days. During this period, temporary lane closures and traffic diversions will be in place. 
  • For more information click on: 7/17 Notification to Neighbors
Asphalt work has begun at the lower grade playground.

July 17, 2024: Asphalt work has begun at the lower grade playground.

Concrete pouring has started at the new entry plaza.

July 17, 2024: Concrete pouring has started at the new entry plaza.

The contractor is setting up forms in preparation for pouring concrete at the new entry plaza.

July 16, 2024: The contractor is setting up forms in preparation for pouring concrete at the new entry plaza.

New trees have been delivered to the site and will be planted soon.

July 16, 2024: New trees have been delivered to the site and will be planted soon.

The form and concrete pours for all curbs in the parking lot are nearly complete.

July 9, 2024: The form and concrete pours for all curbs in the parking lot are nearly complete.

Grading work is in progress.

July 9, 2024: Grading work is in progress.

The concrete curb along the new pick-up/drop-off lane in the parking lot was poured today.

July 1, 2024: The concrete curb along the new pick-up/drop-off lane in the parking lot was poured today.

The forms for the new pick-up/drop-off curb in the parking lot are ready for the concrete pour scheduled for next week.

June 28, 2024: The forms for the new pick-up/drop-off curb in the parking lot are ready for the concrete pour scheduled for next week.

Portables 21 and 22 have been successfully relocated, the parking lot has been completely demolished, and the demolition of the hardcourts has begun.

June 13, 2024: Significant progress has been made since the last day of school.  Portables 21 and 22 have been successfully relocated, the parking lot has been completely demolished, and the demolition of the hardcourts has begun.

May 29, 2024

  • The parking lot entry and exit will remain open on May 31st until 6:00pm.
  • The parking lot and school site will be closed for construction beginning June 1st.
  • For more information click on: 5/29 Notification to School

May 16, 2024:

  • There will be a pedestrian path detour next to the front driveway vehicle entrance starting May 17th so that the contractor can begin work on a new waterline for the fire hydrants.
  • Grading for new portable foundations and work on the new driveway on Cabrillo Ave. will begin the week of May 20th.
  • For more information click on: 5/16 Notification to School

May 10, 2024:

  • New driveway work on Cabrillo Ave. to begin May 20th.
  • Removal of perimeter fencing to begin June 3rd.
  • Installation of perimeter fencing to begin June 20th.
  • Re-striping of traffic lanes on Scott Blvd. to begin July 22nd.
  • For more information click on: 5/10 Notification to Neighbors

May 8, 2024:

  • The date for work to begin on the new driveway on Cabrillo Ave. has moved to May 20th.
  • Beginning June 1st, the school site will be closed for construction.
  • For more information click on: 5/8 Notification to School

April 12, 2024:

  • In order to complete the parking lot and areas directly influencing students prior to the start of school in August 2024, the contractor will start preparing the site during the spring break, April 15th to April 18th.
  • For more information click on: 4/12 Notification to Neighbors

March 29, 2024:

  • The award of contract to SC Builders was approved at the March 28th Board Meeting. 

March 27, 2024:

Questions

If you have questions or would like to be added to the listserv for this project, please email us at ScottLaneConstruction@scusd.net.