New Laurelwood Elementary School
The project will construct a new elementary school at the former Patrick Henry Intermediate School located at 1095 Dunford Way, Sunnyvale, CA including new single-story classroom buildings, multipurpose and administration buildings.The school is scheduled to open in the Fall of 2026.

Project Updates as of June, 2026:
- The Project is being implemented in phases:
- Off-site development (utilities and street improvements) phases one and two.
- Increment 1: Site Grading and Underground Utilities.
- Increment 2: Building and Site Construction.
- Turf field under construction.
- Parking lots and drives ready for asphalt.
- PG&E electrical service projected on June 5 (1,122 days from first application for service.).
- New sidewalks on Teal Drive are complete.
- The school is on track to open in August 2026.
Photos April and June, 2026:









Contact
Rosiella Defensor
Senior Project Manager, Bond Program
(408) 423-3244
rdefensor@scusd.net
Project Links:
-
Design Development Board Update November 9, 2023
-
Schematic Design Board Report February 9, 2023