Briarwood Elementary Modernization

Project Updates as of June, 2026:

The Work is divided into phases beginning with site work summer 2025. Work will extend into the 2025-26 school year. All projects phases will be completed by the end of 2026:

  • New parking lot and drives.
  • Two new classrooms buildings with six classrooms and support spaces.
  • New preschool/K playground with shade.
  • Roofing is complete. Solar panel supports in place. 
  • Interior drywall is underway 
  • The Verkada security and access systems are being incorporated into the project. 
  • Work is commencing on the new lots, drives and Townsend Avenue street improvements. 
  • A plan showing the trees to be retained and removed is on the District website at https://www.santaclarausd.org/about-us/departments/bond-projects/briarwood-elementary-modernization 
Architect rendering of the new Briarwood classroom buildings
Architect rendering of the new Briarwood TK classrooms

Briarwood Modernization Site Plan

Site Plan of the new Briarwood Elementary School Modernization

Briarwood Tree Site Plan

Briarwood Modernization - Tree Protection and Demo Plan_2025-03-25